news release
TO ALL NEWS AND BUSINESS EDITORS
The following contracts below $15,000,000.00 have been endorsed by the National Contracts Commission during February 2003 for award, under the provision of Section 23D(1)(b) of the Contractor-General Act:
|
DATE |
GOVERNMENT AGENCY |
CONTRACT DESCRIPTION |
CONTRACTOR |
CONTRACT VALUE J$ (unless otherwise stated) |
|
05.02.03 |
Ministry of Education, Youth and Culture |
Licence Fees to reprint primary textbooks (2003) |
GINN Educational Publishers |
£ 76,537.50 |
|
05.02.03 |
Ministry of Education, Youth and Culture |
Licence Fees to reprint primary textbooks (2003) |
Jamaica Publishing House |
$ 7,830,000.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Trelawny Package 1 |
Quality Engineering |
$ 5,396,253.50 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Trelawny Package 2 |
Quality Engineering |
$ 5,890,086.40 |
|
12.02.03
|
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. James Package 1 |
Elkims Construction Co. Ltd. |
$ 4,189,875.80 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Hanover Package 1 |
Caleb Construction Co. Ltd. |
$ 5,164,830.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Elizabeth Package 1 |
Mitchell's Construction Co. Ltd. |
$ 7,166,730.23 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Elizabeth Package 2 |
Coldar Construction |
$ 4,127,492.60 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Elizabeth Package 4 |
Coudas Construction Co. Ltd. |
$ 5,646,452.90 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Ann Package 2 |
Woolery Chambers & Hylton |
$ 5,418,092.63 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Ann Package 3 |
Gabions & Structures |
$ 4,272,548.50 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Ann Package 4 |
L&K Construction Co. Ltd. |
$ 4,224,627.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Ann Package 5 |
Melody Heavy Equipment |
$ 5,646,148.75 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Andrew Package 1 |
Mega-B Construction |
$ 4,422,154.88 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Andrew Package 3 |
DP Enterprise |
$ 5,990,028.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Clarendon Package 2 |
S.G. Simpson Asphalting Co. Ltd. |
$ 7,501,029.80 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Clarendon Package 3 |
S.G. Simpson Asphalting Co. Ltd. |
$ 5,780,662.80 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - Clarendon Package 5 |
Lester Johnson Construction |
$ 7,517,350.50 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Mary Package 1 |
Pord Construction |
$ 6,670,378.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Mary Package 2 |
DP Entgerprise Co. Ltd. |
$ 5,006,815.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase VI - St. Mary Package 3 |
Beecher Construction |
$ 4,864,746.15 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase V - St. Thomas Package 4 |
KK Construction |
$ 4,376,355.50 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase V - St. Catherine Package 6 |
Mitchell's Construction |
$ 4,590,398.00 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase V - Manchester Package 5 |
Bacchus Engineering |
$ 4,444,591.19 |
|
12.02.03 |
National Works Agency |
Routine Maintenance of Roads Programme Interim Phase V - Westmoreland Package 3 |
Alwill & Associates |
$ 4,944,720.00 |
|
12.02.03 |
Ministry of Agriculture |
Rehabilitation of the Cedar Valley to Moy Hall parochial and farm access road in St. Thomas |
V.O. Watson and Oneil Associates |
$ 7,981,005.00 |
|
12.02.03 |
Jamaica Social Investment Fund |
Brighton Basic School Completion |
SWC Woodwork & Construction Co. Ltd. |
$ 4,841,490.00 |
|
12.02.03 |
Jamaica Social Investment Fund |
Delveland Basic School Completion |
Howard Construction Company Limited |
$ 5,481,978.60 |
|
12.02.03 |
Jamaica Social Investment Fund |
Longwood Basic School Construction |
Howard Construction Company Limited |
$ 6,037,157.76 |
|
12.02.03 |
Jamaica Social Investment Fund |
Lower Litchfield Basic School Construction |
W.A. Reid Construction Company Limited |
$ 7,183,115.00 |
|
12.02.03 |
Jamaica Social Investment Fund |
Craighead to Bigwoods Road Rehabilitation |
SWC Woodwork & Construction Co. Ltd. |
$ 5,835,750.00 |
|
12.02.03 |
National Water Commission |
National Water Commission's Uniform Supply Programme 2003 - To supply light cotton shirts |
Fabric Consultants Limited |
$ 4,668,663.40 |
|
12.02.03 |
National Water Commission |
National Water Commission's Uniform Supply Programme 2003 - To supply shirts, male dockers type pants |
Satisfaction 2000 Limited |
$ 10,723,083.00 |
|
19.02.03 |
HEART Trust/NTA |
Supply and Installation of Automotive Training Equipment at Cornwall Automotive Training Institute, CATI |
National Supply Company Limited |
US$ 171,565.00 |
|
19.02.03 |
Public Sector Modernization Project (Cabinet Office) |
Supply and Install Computer Hardware and Software in Internal Audit Department |
Illuminat (Jamaica) Limited |
US$ 92,577.44 |
|
26.02.03 |
National Water Commission |
Water Resources Monitoring and Yield Testing of the Orange River Lime Stone Aquifer in Logwood Hanover |
Hydrology Consultants Limited |
$ 7,296,800.00 |
|
26.02.03 |
Development Bank of Jamaica Limited |
Replacement and Upgrade to existing Air Conditioning system at the Development Bank of Jamaica Limited |
Geddes Refrigeration Limited |
$ 6,448,140.24 |
Contracts valued over $15,000,000.00 are subject to approval by Cabinet.
Contact:
Andrea Hoo FungCommunications Officer
Office of the Contractor-General
17 Knutsford Boulevard
Kingston 5
Date:
March 21, 2003